Pulp & Paper Projects

Bowater Canada
Dolbeau, Québec

LMC/QUALMEC converted an oil burning Foster Wheeler boiler to a Kvaerner Power B.F.B. (Bubbling Fluidized Bed) boiler, all within a six-week shutdown period. This fast-track conversion project included the installation of the fuel-feed system, upgrade of the tubular air heater, addition of a radiant super-heater and addition of a new combustion air system.

All of these modifications and upgrades were necessary to provide reliable steam to a new turbine and the mill steam supply. This successful project became the basis of a business relationship where Qualmec performed the maintenance to the unit on a regular basis.

Irving Tissue
Saint John, New Brunswick

  • Installation of a new Metso Tissue Machine at the Irving Tissue plant in Saint John, New Brunswick.
  • The old machine was demolished in 72 hours, including removal of Yankee hood and installing a jacking frame for the Yankee Dryer (a 50-tonne piece of equipment).
  • Installation of new soleplates, including developing a new epoxy grouting procedure for new plates that were placed over existing ones, and erection of the new machine, including the reel section and Yankee hood, accomplished in 18 days.
  • Complete project management, from schedule development, unloading and staging the components, to developing innovative strategies for handling a modular erection of the new tissue machine, for a 21-day sheet-to-sheet outage.
  • Removal of two building columns and installation of a new composite roof support beam to accommodate a larger opening for the Yankee hood air system ductwork.